DOG PARK – We’ve moved 6,670 truck loads of earthworks and 340 truck loads of rock for open drains. Added 180m of asphalt access road, 23 car parking spaces, and set up water, sewer, and electrical services!
Plus, 460m of internal footpaths and a Council inspection means we’re ready for the next phase! 🌳